The comprehensive studies, reconnaissance and design of the dam and power plant commenced on Feb 1989 , as well as construction operations in the summer of 1994. In1997, the water diversion operation was carried out and the dam body was concreted and erected on Oct 2004 which was followed log the filing process in Nov 2004 the plant is generating 500 MW of hydroelectric energy at the time being .
|
|||||||||||||||||||||||||||||
Geographical location: |
|||||||||||||||||||||||||||||
|
28
km of east of Izeh
town at north –
east of Khuzestan province.
|
|||||||||||||||||||||||||||||
|
Objectives and
benefits of the project: |
|||||||||||||||||||||||||||||
|
¯ Generating annually 4137 million KWH hydroelectric energy by a 2000 MW
power plant (that can be extended to 3000 MW). ¯ Controlling the floods and supplying approximately one billion m3 water for
irrigation . ¯ Increasing about % 60 of hydroelectric energy of the country and %2.7 of the total electricity generated in the country in proportion to the existing
status.
¯
Approximately 200 million Dollars of annual benefit. |
|||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||